This dialog appears when you close the Tie Seismic dialog box after specifying tie points.
| With this feature... | Do this... |
|---|---|
| Shift Synthetic | Select whether to shift the synthetic relative to the seismic. This option is available where the slider control i the Cross Correlation Function of the Tie Seismic dialog box is dragged above the zero to a negative value. |
| Time Datum | If the Shift Synthetic option (described above) is active, specify the datum depth to add a zone above the seismic. |
| Correction Velocity | This value is automatically created based on the time datum and shift applied above, but you can change it. |
| Shift Seismic | Specify that the seismic shift relative to the synthetic. |
Parent Topics
| Tying Seismic to Models | Tie Seismic Dialog Box |